Operation CHARM: Car repair manuals for everyone.

AIR Pump Intermediate Pipe/Hose Replacement - Bank 1

SECONDARY AIR INJECTION (AIR) PUMP INTERMEDIATE PIPE/HOSE REPLACEMENT - BANK 1

REMOVAL PROCEDURE
1. Loosen and lower pinch clamp connecting the bank 1 intermediate pipe/hose to the crossover pipe/hose.
2. Loosen and lower the pinch clamp connecting the bank 1 intermediate pipe/hose to the secondary air injection (AIR) shut-off valve.
3. Remove the nut securing the bank 1 intermediate pipe/hose to the transaxle.
4. Remove the nut securing the bank 1 intermediate pipe/hose to the AIR shut-off valve bracket.
5. Disconnect the exhaust gas recirculation (EGR) pipe.
6. Carefully remove the bank 1 intermediate pipe/hose from the engine.

INSTALLATION PROCEDURE
1. Carefully install the bank 1 intermediate pipe/hose.

NOTE: Refer to Fastener Notice in Service Precautions.

2. Reconnect the EGR pipe.

Tighten
Tighten the EGR pipe to 60 Nm (44 lb ft).

3. Install the nuts securing the bank 1 intermediate pipe/hose to the AIR shut-off valve bracket and the transaxle

Tighten
Tighten the nuts to 9 Nm (80 lb in).

4. Install the hose and pinch clamp connecting the bank 1 intermediate pipe/hose to the AIR shut-off valve.

5. Install the hose and pinch clamp connecting the bank 1 intermediate pipe/hose to the AIR crossover pipe/hose.