Standard HoursManufacturer Warranty HoursSkill LevelNotes
Replace
One CYL
Right Bank19.714.6AIncludes: R&I Cylinder Head & Oil Pan, Remove Carbon, Hone Cylinders.
Left Bank19.715.2AIncludes: R&I Cylinder Head & Oil Pan, Remove Carbon, Hone Cylinders.
Both Banks23.517.0AIncludes: R&I Cylinder Head & Oil Pan, Remove Carbon, Hone Cylinders.
Each Additional0.50.3AIncludes: R&I Cylinder Head & Oil Pan, Remove Carbon, Hone Cylinders.
All Cyls
Right Bank22.016.3AIncludes: R&I Cylinder Head & Oil Pan, Remove Carbon, Hone Cylinders.
Left Bank22.016.9AIncludes: R&I Cylinder Head & Oil Pan, Remove Carbon, Hone Cylinders.
Both Banks28.120.4AIncludes: R&I Cylinder Head & Oil Pan, Remove Carbon, Hone Cylinders.
NOTE
To Grind Valves, Add
Both Banks4.43.8A
Tune-Up, Add0.90.0A
To R&R Piston, Pin or Connecting Rod, Add
One0.20.0A
Each Additional0.10.0A
All0.90.0A
To R&R Timing Chain, Add
Primary5.40.0A
Secondary
Right Bank4.90.0A
Left Bank5.20.0A