Installation
P410 HYBRID TRANSMISSION / TRANSAXLE: SHIFT LEVER: INSTALLATION
1. INSTALL SHIFT LOCK CONTROL UNIT ASSEMBLY
(a) Install the shift lock control unit assembly with the 3 nuts.
Torque : 12 Nm (122 kgf-cm, 9 ft-lbf)
(b) Connect the connector to the shift lock control unit assembly.
2. INSTALL LOWER CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY Installation
3. INSTALL INTEGRATION CONTROL AND PANEL ASSEMBLY Installation
4. CONNECT CABLE TO AUXILIARY BATTERY NEGATIVE TERMINAL
5. INSTALL DECK FLOOR BOX RH Installation
6. INSTALL REAR NO. 3 FLOOR BOARD Installation
7. INSPECT SHIFT LEVER
(a) Turn the power switch on (READY).
(b) Check that all available shift positions can be selected moving the shift lever.
HINT
After the shift lock control unit assembly is replaced with a new one, perform the above operation. If this operation is not performed, moving the shift lever may not initially select shift positions.